How long will it take to fill the reservoir? Print E-mail
The initial estimate for the time it will take to fill the Hard Labor Creek Regional Reservoir is 2 1/2 to 3 years depending on rainfall.  The Georgia Safe Dams Program sets guidelines for safely filling a reservoir. The rate is based on the height of the dam. For the first one-third of it, the reservoir can be filled at an uncontrolled rate. The maximum rate for the second third is two feet per week; for the final third it’s one foot per week. This controlled pace helps assure the safety of the dam in holding back the water.
 