Status

  • USACOE 404 Permit: Approved February 2004
  • Georgia EPD Water Withdrawal Permits: Approved June 2008
  • Land Acquisition:  Complete
  • Stream/Wetland Mitigation: Complete
  • Water Intake Structure:  August 2014
  • Road Relocation:  January 2015
  • Dam/Reservoir Construction:  March-April 2015
  • Reservoir Fills: 2015 - 2016
  • Reservoir Full Pool: 2017